The short answer
IBM i is a living platform, so teams rarely come to Ace8 to leave it. They come because a release is past standard service, hardware is due, or the RPG team is thinning. Ace8 does the assessment and plan, and the IBM i work is delivered with a vetted specialist partner. Ace8 claims no past IBM i projects.
Which IBM i situation are you in?
Three typical situations, each with its trigger and first step. The sections below cover the risks, the approach and the fit.
| Use case | Trigger | First step |
|---|---|---|
| The system runs IBM i 7.3 or 7.4 after the service level change | IBM i 7.4 change in service level 30 Sep 2026 | Ace8 assessment, partner delivery |
| A Power server refresh forces the OS and application question | 7.6 supported on selected Power11, Power10 | Ace8 assessment, partner delivery |
| The RPG team is thinning and the board asks about a rewrite | 69% of IBM i shops name skills a top concern | Ace8 assessment, partner delivery |
What should you do when IBM i 7.3 or 7.4 reaches its change in service level?
Check the date and the extension terms with IBM, then decide on the next release. IBM lists 7.3 at 30 Sep 2023 and 7.4 at 30 Sep 2026, with a Service Extension Offering after each. Upgrading the OS does not fix the application debt.
| Situation | The system runs IBM i 7.3 or 7.4 after the service level change |
|---|---|
| Trigger | IBM i 7.4 change in service level 30 Sep 2026 |
| First step | Fixed-price assessment and plan by Ace8 |
| Delivered by | Ace8 plan, delivered with a vetted specialist partner |
| Service | IBM i modernization |
The situation
An IT manager runs core order, billing or inventory systems on IBM i 7.3 or 7.4. The operating system upgrade is on the roadmap, but nobody has checked whether the custom RPG and CL programs, third-party packages and hardware will go along.
What makes it urgent
IBM's release life cycle table lists the change in service level for IBM i 7.3 as 30 Sep 2023 and for 7.4 as 30 Sep 2026. It says the Service Extension Offering for 7.4 starts on October 1, 2026 and ends September 30, 2029, and for 7.3 runs through September 30, 2028. For 7.5 and 7.6 no date has been set, and IBM says it will announce one with at least 12 months' notice.
Risks and constraints
- Third-party packages and in-house exits may be certified for specific releases only.
- The extension is a way to buy time, not a plan, and its terms need to be checked with IBM.
- Moving to 7.6 may also mean new hardware, which turns an OS upgrade into a larger project.
- Old programs with no tests make every release change a gamble.
How Ace8 handles it
Assess
Inventory programs, display and printer files, job schedules, data areas, Db2 for i objects and third-party products, with their release dependencies. Rank each by business value, change rate and test cover.
Decide
Lay out the upgrade path, the extension option and the application work as one plan with dates. Any IBM i code or platform work is delivered with a vetted specialist partner.
Run
Rehearse the upgrade on a copy first, compare results on recorded inputs, and keep a way back. AceMQ supports the platform 24/7 after the move.
What you get
- Release and dependency map: OS, packages and in-house code
- Upgrade plan with dates, tied to IBM's published lifecycle
- Program list ranked by risk and test cover
- Rehearsal results on recorded inputs and outputs
A fit when
- You are on 7.3 or 7.4 and want one plan for the OS, the packages and your own code.
- You need evidence for a budget request, not a general warning.
Not a fit when
- You only need IBM's extension terms. Ask IBM or your business partner for those.
- You are already on 7.5 or 7.6 and the code is well covered by tests. The urgency is not there.
Sources
- IBM: IBM i release life cycle: 7.3 and 7.4 change in service level dates; Service Extension Offering terms; 7.5 and 7.6 notice (checked 23 Nov 2026)
How does a Power hardware refresh affect an IBM i application estate?
It ties the OS release to the hardware. IBM lists IBM i 7.6 as supported on selected Power11 and Power10 servers, so a new server can decide the release. Plan the upgrade, the package certifications and the code testing together, not as three separate projects.
| Situation | A Power server refresh forces the OS and application question |
|---|---|
| Trigger | 7.6 supported on selected Power11, Power10 |
| First step | Fixed-price assessment and plan by Ace8 |
| Delivered by | Ace8 plan, delivered with a vetted specialist partner |
| Service | IBM i modernization |
The situation
An infrastructure lead has a server at the end of its lease or maintenance term, or a data center that is closing. The business wants the move done once. Application owners fear that any change to the OS or hardware will surface problems in programs nobody has touched for years.
What makes it urgent
IBM's IBM i 7.6 base enhancements page says the release is supported on selected IBM Power servers with Power11 and Power10 processors, and lists the models, with minimum firmware FW1060 for Power10 and FW1110 for Power11. IBM's life cycle table gives 7.6 general availability as 04/18/2025.
Risks and constraints
- The target release and the hardware must be checked against IBM's model list before ordering.
- A one-weekend cutover leaves no room to find that a package does not run on the new release.
- Job schedules, data areas and interfaces often hold undocumented dependencies.
- Old and new systems need to run in parallel long enough to compare results.
How Ace8 handles it
Assess
Map the current release and hardware to IBM's model list for the target. Inventory packages, in-house programs and external interfaces, and record real inputs and outputs from the month-end and batch cycles.
Decide
Choose the route per workload: move as is, modernize first, or re-host elsewhere. Platform and code changes are delivered with a vetted specialist partner, with Ace8 holding the plan and the test evidence.
Run
Run the old and new systems side by side, compare results on the recorded cycles, then cut over with the old system kept ready for a rollback. AceMQ supports the new setup 24/7.
What you get
- Hardware and release compatibility check against IBM's model list
- Workload inventory with a route for each
- Recorded batch and month-end baselines
- Cutover plan with a documented rollback
A fit when
- You have a hardware or data center date and want one coordinated plan.
- You want evidence that the new system matches the old on real cycles.
Not a fit when
- You are buying a like-for-like replacement, the release stays the same and your hardware partner is handling the move.
- The server is not near end of life and no date is forcing the move.
Sources
- IBM: IBM i 7.6 base enhancements: 7.6 supported on selected Power11 and Power10 servers; minimum firmware (checked 23 Nov 2026)
- IBM: IBM i release life cycle: 7.6 general availability 04/18/2025 (checked 23 Nov 2026)
Should you keep IBM i and expose APIs, or rewrite the RPG applications?
Start by deciding which programs earn a change. Keeping IBM i, modernizing RPG and exposing services is often the lowest-risk route for stable core logic. A rewrite fits where the business needs something the platform cannot give. Skills risk can be handled either way.
| Situation | The RPG team is thinning and the board asks about a rewrite |
|---|---|
| Trigger | 69% of IBM i shops name skills a top concern |
| First step | Fixed-price assessment and plan by Ace8 |
| Delivered by | Ace8 plan, delivered with a vetted specialist partner |
| Service | IBM i modernization |
The situation
A CIO or application owner has core business logic in RPG that has run for decades. The two people who know it best are near retirement, and recruiting is slow. A new executive has asked why the company is not moving everything to Java or a SaaS package.
What makes it urgent
IT Jungle reports that in Fortra's 2026 IBM i Marketplace Survey, 69% of 315 respondents ranked finding people with IBM i skills as a top concern, the first time it has led the list. It also reports that application modernization was a top concern for 62%, and cybersecurity for 64%.
Risks and constraints
- Business rules in old RPG may be documented nowhere else.
- A rewrite takes the whole estate at once, while most programs are stable and rarely change.
- Wrapping with APIs keeps the RPG skills dependency, so knowledge transfer still has to happen.
- Survey data is a view of the IBM i community and does not describe your estate.
How Ace8 handles it
Assess
Score every program by business value, change frequency and test cover, and capture the rules as runnable examples, not prose. This builds the knowledge record before the people leave.
Decide
Give each program a route: keep, modernize in place, expose through APIs, or rewrite. Show the cost drivers and the risks of each. IBM i work is delivered with a vetted specialist partner.
Run
Change one slice at a time, check each against the recorded examples, and keep the RPG version as the fallback until the new one is proven. AceMQ supports the result 24/7.
What you get
- Program inventory with a route for each
- Business rules captured as runnable examples
- API candidates: which services to expose first
- Decision paper for the board: keep, wrap or rewrite, with risks
A fit when
- You depend on a few RPG experts and want their knowledge captured and tested.
- You need to answer a rewrite question with evidence.
Not a fit when
- You already have a funded replacement and only need data migrated.
- The estate is small and stable and you can hire. Keep investing in the platform and the team.
Sources
- IT Jungle: Skills displaces cybersecurity as top concern for IBM i shops (reporting Fortra's 2026 IBM i Marketplace Survey): 69% of 315 respondents rank skills a top concern; 62% application modernization; 64% cybersecurity (checked 23 Nov 2026)
Frequently asked questions
When does IBM i 7.4 reach its change in service level?
IBM's life cycle table lists September 30, 2026 for IBM i 7.4. IBM's Service Extension Offering for 7.4 starts on October 1, 2026 and ends September 30, 2029. Check terms and cost with IBM.
Is IBM i going away?
IBM's table lists IBM i 7.6, with general availability on 04/18/2025, and no end date has been set for 7.5 or 7.6. IBM says it will give at least 12 months' notice before one is set.
Does Ace8 have IBM i projects to show?
No. Ace8 claims no past IBM i projects. Ace8 does the assessment and plan, and the IBM i work is delivered with a vetted specialist partner. The first phase is fixed price after a scoping call.
How big is the IBM i skills problem?
In Fortra's 2026 IBM i Marketplace Survey, as reported by IT Jungle, 69% of 315 respondents named finding people with IBM i skills a top concern. It was 60% the year before.
Get a fixed scope and price before anything moves.
A fixed-price assessment gives you the inventory, the risk score and a phased plan.